KEE SERVICES LIMITED – REFURBISHMENT OF EXISTING TREATMENT SYSTEMS FOR IMPROVED PROCESS PERFORMANCE AND REDUCED LIFETIME COSTS

KEE Refurbishment of Packaged Treatment Plants

The Anglian Water Systems (AWS) Team undertook such an exercise over a range of small to medium sized treatment plants adapted by the plc from a local council. Instead of abandoning the existing works, KEE Services Ltd with support from their process partners, KEE Process Ltd, were commissioned to survey 11 sites and report the findings. The report was required to include inventory register, feasibility of refurbishment, process implications and improvements with the associated costs of refurbishment. The survey was undertaken and completed over four weeks and a complete report, with a costed refurbishment program for all the sites was submitted to the AWS Team.

The 11 plants varied from 40PE up to 500PE in size and included systems required to reduce BOD and, in some instances, provide fully nitrified discharge with less than 5mg/l ammoniacal nitrogen. All the plants surveyed were of packaged plant construction, single piece or modular, and included primary settlement stage with combined sludge storage, RBC type biological stage and final settlement tank. The report concluded that it was feasible to refurbish all the plants and included a program for refurbishing the plants to a standard where the operators would have the confidence that the plants would provide a reliable and useful life for a further 20 years. Depending on the extent of refurbishment work necessary, the costs associated with the refurbishment varied substantially, but in every case it was much cheaper than replacement. The cost of refurbishment included for supply and installation of new equipment.

KEE Refurb Sequence-01 KEE Refurb Sequence-02 KEE Refurb Sequence-03KEE Refurb Sequence-04 KEE Refurb Sequence-05 KEE Refurb Sequence-06 KEE Refurb Sequence-07 KEE Refurb Sequence-08

This relates to a cluster of small population equivalent installations where all the plants upgraded were over 20 years old and would now have in excess of a further 20 years life and an improved process performance. With all the sites, the outer GRP structure housing the plant was retained and, with the exception of one or two sites, the internal components including the RBC were replaced by brand new factory built units incorporating the latest concepts in mechanical, structural and process engineering.

All the above plants include sectional GRP covers and were replaced to provide the equivalent of a new plant without the high cost and resource required to build one.

Refurbishing Large Wastewater Treatment Works

The KEE refurbishment concept can also be applied to plants serving larger populations which can be electro-mechanically upgraded to show similar benefits and add 20 years or more useful life to the plant. Scottish Water undertook a similar exercise where an existing 4,750PE activated sludge plant needed to be refurbished to bring the plant back to its full performance requirement without necessarily having to re-build the works.

For more information on Wastewater Treatment Plant refurbishment call KEE Services on: 01296 634500 or visit the KEE Services website.

KEE TRITON AERATOR/MIXER OVERCOMES PREVIOUS LIMITATIONS OF OXIDATION DITCH TECHNOLOGY

KEE FINE BUBBLE AERATION WITH BUILT IN MIXER

Triton-Graphic-(2)

KEE Process Triton

The KEE Triton Aerator/Mixer overcomes the previous limitations of oxidation ditch technology and can be used to revitalise existing oxidation ditches and extended aeration plant or systems based on activated sludge process.

Using the dual mode processor capabilities of Triton Aerator, aeration basins up to depths of 10m can be completely aerated and mixed. Existing Oxidation Ditches (OD) can be retro-fitted and new OD plants benefit with much smaller footprint. Nitrification and denitrification can all take place in a single reactor. With two propellers and a regenerative blower, Triton is able to operate either as an anoxic mixer with the blower turned off, or an efficient aerator/mixer with the blower on.

Multiple Triton units can be arranged to provide extended contact time between air bubbles and water stream, with greater oxygen transfer efficiency. Improved biological treatment results in Biochemical Oxygen Demand (BOD) removal rates as high as 99% in highly contaminated wastewater.

The KEE Triton is the most versatile fine bubble aeration/mixing device for activated sludge treatment systems available with dual functions – aeration and mixing.

KEE fixed price operation and maintenance contracts are available.

For full information on KEE Technologies and Services visit: KEE Fine Bubble Aeration
or call KEE on: 01296 634500

KEE SERVICES LIMITED MAINTAIN WASTEWATER AND SEWAGE TREATMENT EQUIPMENT MADE BY ANY MANFACTURER

Engineer-02

The maintenance and operation of any wastewater treatment equipment is a specialised task and KEE Services Limited recognises this.

KEE, with its extensive experience of on-site servicing of all types of wastewater treatment and pumping equipment, its technicians have the knowledge necessary to protect its customers’ investment and the environment.

KEE Services offers planned maintenance programmes ranging from an annual visit to full plant operation. Its aim is to respond to all of your urgent servicing and maintenance needs. The KEE Services Team of fully trained Technicians operates on both a local and regional basis to ensure a prompt and reliable service.

  • Emergency Services
  • Planned Maintenance
  • Breakdowns
  • Equipment Refurbishment
  • Plant Operation
  • Spares
  • Ancillary Products

Committed to maintaining your environment

KEE Services Ltd offers Preventative Maintenance, Process Operation and Breakdown Services for all types of treatment plant and pumping equipment, from all manufacturers. KEE Services Ltd supports its UK customers during out-of-hours emergencies by offering a 24-hour manned call out service.

KEE Technicians are trained in long-term servicing and look after over 8,000 installations in the UK. They have sound mechanical and electrical experience, combined with application knowledge, and can identify problems early.

Working on a local basis, KEE technicians give a prompt service and have a good understanding of the conditions and legislations in each area.

Service and maintenance contracts include routine visits to keep equipment from both KEE Process and other manufacturers in top condition and prolong its lifespan.

There is a range of contracts available or a package can be designed specifically. If refurbishment or upgrading is necessary, KEE Services can advise on the alternatives. Site assessment can be made and installations planned for new and existing sites.

For full information visit the KEE Services website or call 01296 634500 to arrange a visit.

 

KEE PROCESS LIMITED HAVE DEVELOPED A NEW SINGLE-PIECE FACTORY BUILT WASTEWATER TREATMENT PLANT TO ADD TO THEIR RANGE

Developed by KEE the NuDisc© 5000 HD RBC Sewage Plant and Treatment Centre – a new single-piece factory-built plant to add to their range to meet Severn Trent Water’s extremely stringent requirements.

a

Situated in the heart of the Peak District, the village of Hassop in north Derbyshire lies approximately 11 miles east of Chesterfield and 2 miles to the north of Bakewell, and is within the Severn Trent Water’s catchment. The properties subject to the Section 101a application were served by a village drain. This received flows from septic tank high level overflows and discharged to a local un-named watercourse. Local ground conditions were unsuitable for soakaways. Hassop Estate applied, under Section 101a of the Water Industry Act 1991 in December 2007, for a public sewerage system to be provided.

In 2010 STW accepted the need to lay new sewers and treatment system. The new wastewater treatment works was required to treat flow from a population equivalent of 210, and the consent to discharge for this site required that the BOD < 20mg/l, SS < 30mg/l and NH4-N < 5mg/l.

Project background and cost considerations
The construction of the Hassop WwTW involved the laying of approximately 1600m of foul sewer, an intermediate pumping station and a new RBC Unit to serve the Village. The work was undertaken by NMCNomenca as the Tier 1 Framework Partner and as part of S101A Scheme for Severn Trent Water Ltd.

NMCNomenca’s scope of works was for the detailed design, construction and supervision of the whole project from start to finish. NMCNomenca were also in control of the site until handed back to Severn Trent Water Ltd after commissioning and testing.

The project for capital delivery had to take into account CAPEX and OPEX costs to determine lifetime costs for the project over 20 years. This included the capital cost of delivering the project; design, manufacture, delivery and commissioning of the process plant and all site-related costs including provisions for on-site health & safety, environment and personal welfare for site operatives. The second part of the costs related to operational costs and included cost of energy, consumables, spares, labour and process-related costs such as desludging. The overall objective for the consortium is to minimise lifetime costs without compromising any aspects of the project delivery including site work.

Consent standards
The site at Hassop required to treat wastewater from a population equivalent of 210 with design DWF of 32m3/d, FFT of 173m3/d, BOD load of 12.6kg/d, SS of 15.75kg/d and NH4-N of 1.68kg/d. The consent to discharge for this site required that the BOD< 20mg/l, SS < 30mg/l and NH4-N < 5mg/l.

Such consent standards from the Environment Agency are common for wastewater discharge to a watercourse, although for a small works with such a large variation in design flows during dry and wet weather, this does present a challenge to the designers to ensure that the plant performs to requirements under all these conditions throughout the year.

Process plant selection
KEE Process has, over the last 60 years, developed a range of plants to treat wastewater from municipal and industrial sources to similar and more stringent standards where the BOD values could be less than 5mg/l, SS less than 10mg/l, ammoniacal nitrogen less than 1mg/l, phosphorus less than 1mg/l and total nitrogen less than 15mg/l. The range from KEE includes small packaged systems for small flows, modular packaged units for larger flows and in situ constructed plants for populations larger than 5,000 PE.

For the site at Hassop, the largest single-piece factory-built plant available at the time in KEE’s range was not adequate to deal with the flows, so KEE developed a new single-piece factory-built plant to add to their range. The single-piece plant would be factory built and would take into account all the requirements laid out by Severn Trent Water in its specification and the plant would be delivered to site ready to be placed on a pre-prepared concrete slab and backfilled.

The plant would include installation of the remote desludging facilities and internal electrical wiring during the plant construction in the factory. This would, in effect, be a true ‘plug and play’ system with the objective of reducing site-related construction time and costs.

Building a plant in a factory provides a controlled environment and conducive conditions for maintaining quality standards, which are often difficult when the build is undertaken at a construction site under the prevailing conditions, which may include rain, snow, low temperatures and hazardous operating environment.

In addition, a factory-built plant would enable the duration of construction on site to be substantially reduced, as the factory-built plant can be backfilled within a day or two of being delivered. This means that the excavation is not left open for long periods and, in turn, this reduces any health and safety risks associated with working on site with deep excavations and in confined spaces. However, this may have a major impact on the project costs when plants are factory built compared to building on site.

NuDisc®
KEE NuDisc® 5000 includes the primary sedimentation stage with sludge storage, RBC for biological treatment and a hopper final clarifier, all housed in a single structural GRP housing and covered with lightweight GRP covers.

The RBC is driven by a 0.75kW geared motor at a slow speed of 1rpm and is designed to comply with all the structural and mechanical requirements stipulated by Severn Trent Water Ltd.

The FST includes a fully automated descumming and desludging system, for removal of scum and sludge at regular hourly intervals back to the primary clarifier.

The primary clarifier includes remote desludging facility and this is carried out at regular intervals of 90 days when 18.9m3 (5000 gls) of sludge is tankered away.

KEE packaged plants also include flow attenuation within the primary settlement chamber, in order to provide process stability with the large fluctuations in design flows.

The manner in which the attenuation system is organised also enables evening out peaks and troughs in organic load and this attenuation is achieved in the first stage of the biological process.

Designed and built at KEE’s factory, the KEE NuDisc® 5000 was delivered on time on a cold snowy day and was placed in an excavation ready to be backfilled all on the same day.

The plant was fully commissioned to receive flows only seven weeks from delivery – a big achievement for all the parties involved including KEE Process, NMCNomenca and the client, Severn Trent Water. All other site related matter including landscaping, electrical control gear, remote telemetry system and landscaping were completed within timescales.

Operational and maintenance requirements
The operational and maintenance requirements are desludging every 90 days, lubrication of bearings required every six months. With a daily energy consumption estimated at 21kWh/d. The OPEX costs for the site are therefore minimised.

Summary
Although KEE Process does not have comparative lifetime costs for this specific project, the costs for similar projects with other water companies have shown 30% reduction in capital costs compared to other technologies with substantial amount of site related construction and equally a large proportion of savings in operating costs resulting from savings in energy consumption and operational labour requirement.

KEE, a BSI Certified Company (IMS, QMS, OHS & EMS) offers domestic and industrial wastewater treatment solutions including lifetime operation and maintenance using RBC, SAF, SBR and Extended Aeration. With 60 years’ experience and over 350,000 installations, KEE have the expertise in design, build and operation of all wastewater treatment plants.

For full information on KEE Technologies and Services visit the KEE Group website:

KEE SERVICES LIMITED NOW OFFER TANKERING

Residential or commercial, save time and money by having KEE Services desludge and service your treatment plant.

Most of the times your wastewater treatment system will need no intervention from you to do its work. All it will require is the annual desludging and that’s when KEE Services can help.

We provide a timely, guaranteed and professional service to empty your wastewater system. But that’s not all! We also provide advice and support and can help you to keep everything working sweetly.

Waste water from sinks, baths, showers, dishwashers, washing machines and toilets are plumbed into your foul drainage system. This waste arrives at the wastewater treatment system where the solids settle to the bottom and light materials such as grease, suds etc. float to the top. For every litre that flows into the tank a litre must flow out into the drainage field below the septic tank. There is very little biological treatment within a septic tank, although modern package sewage plants do treat the effluent.

If the tank is not emptied on a regular basis solids will be washed into the drainage field and can cause blockages. These blockages are hard to remove and the most common remedy is to install a new drainage field. This can be very expensive compared to regular emptying.

ForecourtManagement-03 ForecourtManagement-04
KEE Tankering Services                                             or Jetting Services

Why KEE Services Tankering?

Reasons why you should choose KEE Services to empty your Wastewater Treatment System.

  • You get a completely local service from a nationwide company
  • You speak to real people, and will get free advice and help
  • You know that the job will be done well by our highly trained and experienced engineers.
  • The work is guaranteed
  • The price we quote will be the price you pay there are no supplements, call outs or fuel surcharges.

We have been servicing, repairing and emptying wastewater treatment systems for more than 60 years.

Call 01296 634500 to arrange a visit or go to the KEE Services website for more information.

KEE Services Logo

 

REVITALISE OXIDATION DITCHES WITH THE KEE DUAL MODE TRITON AERATOR/MIXER PROCESSOR

KEE – FINE BUBBLE AERATION SYSTEM WITH BUILT-IN MIXER

Triton

The patented new Dual Mode Processor called the Triton Aerator/Mixer.

This new technology overcomes the previous limitations of oxidation ditch technology and can be used to revitalise existing oxidation ditches and technology.

Oxidation ditch technology is one of the oldest ways of treating wastewater. Whilst it enables wastewater to be treated to a high standard, including nitrification and de-nitrification, it does have significant limitations.

The process requires aerated and mixed liquor to continuously move through the aeration ditch. Brush rotors and disc rotors aerate and mix the liquor but, because they can only maintain the necessary fluid velocity of 0.3 – 0.4m/s in a shallow depth of no more than 2m, the footprint area of the oxidation ditch is extremely large.

The Triton Aerator and Mixer Aerator is an energy efficient, dual mode (aeration and mixing) process aerator that is capable of nitrification and de-nitrification all in one unit. With two propellers and a regenerative blower, it is able to operate either as an anoxic mixer with the blower turned off, or a very efficient aerator/mixer with the blower turned on.

With its two mixing propellers, the Triton is able to achieve significant velocities in depths of up to 10m. This means the oxidation ditch basin can now be built up to 10m deep, therefore significantly reducing the footprint area.

The Triton Aerator/Mixer’s primary and secondary propellers inject air bubbles (defined by the Environmental Protection Agency as “fine bubble”) into a high velocity stream (plume) below the surface of the water and provide flow linkage mixing in multiple unit arrangements.

The Triton can also be used to revitalise existing oxidation ditch systems with failing brushes or disc rotors. If the rotors have totally failed, the Triton can replace them.

CASE STUDY

Franklin’s plant has two oxidation ditch systems operating in parallel, each of which treats 4536m3/day, with influent BOD of 185mg/l and TSS of 90mg/l. The Oxidation Ditch Wastewater Treatment Plant at Franklin was failing to meet the consent of 15mg/l BOD and 23mg/l TSS. Because the rotors required daily lubrication, maintaining them was a time consuming and costly exercise. So when the rotors fractured and failed four years ago, the decision was made to upgrade the plant by replacing the brush rotors with the Triton Aerator/Mixer.

During the upgrade each ditch was fitted with four Triton each rated 18.6 kW. This represents a maximum of just over 2kWh of electrical energy per kg of BOD or 0.4 kWh/m3 flow.

The final effluent quality from the refurbished oxidation ditch is testimony to the excellence of the Triton. The result of the upgrade was final effluent with BOD of between 2 and 3mg/l and TSS well below 15mg/l. Independent velocity measurements at extremities are well above the minimum 0.3m/sec, therefore guaranteeing that no solids deposit would develop in the basin. At the same time, maintenance requirements have been substantially reduced to a simple lubrication task once every six months.

For full information on KEE Fine Bubble Aeration visit:
http://www.fine-bubble-aeration.co.uk/

For full information on KEE Technologies and Services visit:
http://www.keegroup.co.uk

KEE BIO-GUARD – THE BIOLOGICAL SOLUTION AGAINST FAT, OIL AND GREASE – THAT CLEARLY PROVIDES BETTER RESULTS – 15% off all new orders

Ancillary-04
Ordering replacement dosing liquid:

KEE provide an extremely cost competitive dosing liquid for the Grease Digester Bio-Guard system, which is compatible with all other manufacturers FOG system equipment.

Contact KEE today on
01296 634500
to arrange for a free no obligation quotation to resolve your fat, oil and grease issue.

Busy kitchen environments regularly suffer from the unnecessary build up of fats and grease due to food preparation and dish washing.

When left untreated on a regular basis, the build up of fats and grease can result in many common problems such as;

  • Frequent emptying of fat traps.
  • Hygiene concerns.
  • Unpleasant odours.
  • Emergency rodding.
  • Unnecessary and expensive emergency call out charges.
  • Disruptions to services from blocked drains.
  • Damage from flooding as a result of blocked drains.
  • Lost revenue.

The Permanent Solution.
The KEE Bio-Guard technology provides a simple and permanent, long lasting solution to the unwanted build up of fat and grease in the drains, thereby reducing the associated risks of blocked drains in the food preparation and cooking areas.

KEE Bio-Guard benefits:

  • Free running drains.
  • Conformity with effluent treatment regulations.
  • An environmentally friendly response to a pollution problem.
  • Automatic dosing avoiding human error.
  • Control of operational costs.
  • Peace of mind.

The automatic dosing system is normally wall mounted with the reservoir of liquid stored at ground level and regularly provides an accurate dose of the liquid biological solution containing micro-organisms specially selected to degrade fat, oil and grease in fat traps and drain lines.

Cost Effective Technology.
The KEE Bio-Guard technology is very cost effective both from a capital and operational aspect when compared to other similar systems currently on the market. This cost effectiveness is without compromising the overall system efficacy and operation.

Ease of Installation.
Installation is very simple. For the operation of the KEE Bio-Guard system, a 240 Volt single-phase non-switchable fused spur local to the system is required.

For full information on the KEE Bio-Guard visit:
http://www.keebioguard.com/

For full information on KEE Technologies and Services visit:
http://www.keegroup.co.uk